Oct 2022 – Roof and sidings and Mikvah Stairs
Oct 2022 – Roof and sidings and Mikvah Stairs Read More »
Foundation of building walls and floor slab setup
Aug 2022 – Foundations Read More »
Mikvah waterproofed and forms set in place and then the most exciting part, the actual formation of the mikvah! Rabbi Katz came down to supervise the mikvah pouring.
July 2022 – Mikvah Poured! Read More »
April – Cradle Section is being dug out Floor of the cradle poured Floor of the cradle
April 2022 – Cradle Floor Read More »
March 2022 – Construction has started with Underpinning the house to support the mikvah
Construction Started Read More »