Aug 2022 – Foundations
Foundation of building walls and floor slab setup
July 2022 – Mikvah Poured!
Mikvah waterproofed and forms set in place and then the most exciting part, the actual formation of the mikvah! Rabbi Katz came down to supervise the mikvah pouring.
June 2022 – Cradle and Soak
Cradle formed and now can soak
May 2022 – Cradle Walls
Next the Cradle walls are going up
April 2022 – Cradle Floor
April – Cradle Section is being dug out Floor of the cradle poured Floor of the cradle
Construction Started
March 2022 – Construction has started with Underpinning the house to support the mikvah
First Steps
Before we can start we needed to clear some branches