Oct 2022 – Roof and sidings and Mikvah Stairs

Uncategorized / Admin23

Oct 2022 – Roof and sidings and Mikvah Stairs Read More »

Sept 2022 – Walls Going up

Uncategorized / Admin23

Sept 2022 – Walls Going up Read More »

Aug 2022 – Foundations

Uncategorized / Admin23

Foundation of building walls and floor slab setup

Aug 2022 – Foundations Read More »

July 2022 – Mikvah Poured!

Uncategorized / Admin23

Mikvah waterproofed and forms set in place and then the most exciting part, the actual formation of the mikvah! Rabbi Katz came down to supervise the mikvah pouring.

July 2022 – Mikvah Poured! Read More »

June 2022 – Cradle and Soak

Uncategorized / Admin23

Cradle formed and now can soak

June 2022 – Cradle and Soak Read More »

May 2022 – Cradle Walls

Uncategorized / Admin23

Next the Cradle walls are going up

May 2022 – Cradle Walls Read More »

April 2022 – Cradle Floor

Uncategorized / Admin23

April – Cradle Section is being dug out Floor of the cradle poured Floor of the cradle

April 2022 – Cradle Floor Read More »

Construction Started

Uncategorized / Admin23

March 2022 – Construction has started with Underpinning the house to support the mikvah

Construction Started Read More »

Fundraising Week

Uncategorized / Admin23

Fundraising Week Read More »

First Steps

Uncategorized / Admin23

Before we can start we needed to clear some branches

First Steps Read More »